Saturday 18 January 2014

Week 8

Well I hadn't been at the block for a couple of weeks, we have been on the tail end of the traditional Christmas break and for the past week have experienced 40c+ days almost every day.

I really wasn't expecting there to be any progress at all on our build. But to my surprise I found that the plumbing had been done, the air conditioning and heating had been roughed in, bricks and sand delivered, plaster and cornice sitting in my family area. Front door was fitted as well, I was really pleased.

Brickwork is due to start on Monday, still waiting for my Alfresco/Family room door to be replaced, hope this is done really soon so it doesn't affect the brickies.